Configuring Costs is the third step in setting up your Scenario, following the configuration of the Forecast and Operations sections. Detailed guides for these steps are available in our Knowledge Base.
Cost configuration is not a hard requirement. You can still use many of SimPath's features, such as visualisations or Asset-Distance optimisation, before fully modelling your costs. However, entering cost parameters unlocks exploration of your cost drivers, as well as valuable insights from cost-driven optimisations.
To begin, navigate to the Scenario you are configuring and click on Add Transport Costs. This will take you to the Transport Costs Configuration page.
The default transport mode is Road. Other modes such as Air or Sea may be available depending on your subscription. The Default Road transport mode has unlimited capacity.
There are two primary cost types:
Most transport cost models use a combination of both. You can set either value to zero if it doesn't apply to your model.
Just like Facility Costs, you can model economies of scale using the Add Tier button — for example, lower relative costs per unit for larger shipments. In the demo, we renamed the Default tier as Large and added a Medium tier with slightly higher costs and lower capacity. You can add as many tiers as needed.
Click Save to complete your Transport Cost configuration.
For more detailed transport cost models, Advanced Configuration is also available. See the Advanced Transport Configuration article in our Knowledge Base.